I am a General contractor looking for pricing on a project for our client.  This is a single story commercial strip mall.  The space is mostly open and measures approximately 38 x140.  The scope of work is as follows:

Demolition General demo throughout, All VCT tile, ALL interior partitions, all drop ceiling and grid. Remove all existing interior NON-Load Bearing partitions (~90LF), Existing wood stud walls (CMU wall and demising ~280LF), all wall paneling, bathroom core walls, existing ACT ceiling tile/grid, Lighting and existing checkerboard/VCT floor finish throughout. (Owner will provide testing and report) 5,300 SF
Ceilings New 2x4 ACT Panels + Grid (Materials) Procure 2x4 ACT (Rockfon Artic 601 square edge) ceiling system with 9/16" Standard white grid, hanger wire, wall angle, 2x4 ACT panels. Hung on Wire (Black Iron Excluded). 5,800 SF
Ceilings New 2x4 ACT Panels + Grid (Labor) Furnish/install new 2x4 ACT ceiling system with 9/16" grid. NO insulation above drop ceiling. Plenum space utilities and HVAC repairs by others NOT part of this quote. Blackiron, Sprinkler and mechanical work NOT part of this quote unless specified in bid 5,300 SF
Flooring Glue-down LVT materials Procure Owner-selected glue-down LVT (5$ per SF allowance) 5300 SF
Flooring Glue-down LVT install labor Install glue-down LVT & cove base 5300 SF
Carpentry Doors / frames / hardware New restroom/core doors, frames, hardware, signage where shown, Solid Core Wood Veneer, Metal Buck, Schlage Locks, as per owner supplied plan 3 EA
Carpentry Blocking / accessories backing Blocking / Mounting for grab bars, mirrors, accessories, toilet, sink 2 EA
Carpentry / Framing Restroom/core framing (up to 12ft AFF) Frame new restroom/Utility partitions and affected wall/door openings, above grid, as per plan. 3-5/8", 20 ga. metal studs at 16" O.C., 5/8" gypsum board both sides, water-resistant gypsum board on wet sides where indicated, sound attenuation batts where indicated, extending to 6" above finished ceiling. Non-Fire rated partitions. 44 LF
Carpentry / Framing Exterior and Demising wall framing (up to 12ft AFF) Frame all exterior cmu walls, demising wall, rear wall, front wall with 3-5/8", 20 ga. metal studs at 16" O.C., extending to 6" above finished ceiling. NON-Fire rated NON insulated. 357 LF
Carpentry / Drywall Drywall Materials (up to 12ft AFF) Procure commercial 5/8" sheetrock and related materials at restroom/core and all interior walls, up to 12ft AFF. 122 SH
Carpentry / Drywall Drywall Labor (up to 12ft AFF) Hang/finish/Paint Level III, commercial 5/8" sheetrock at restroom/core and wall repairs as required. Includes Paint as per plan. Extends 12ft AFF. Fire rating and certifications NOT included (provided by owner) 122 SH
Carpentry / Drywall/Paint Paint (Benjamin Moore Materials) Procure Paint for walls. Premium Paint Benjamin Moore "BEN" Pale Oak OC-20 eggshell or selected color. (Paint Labor to be Priced inside drywall numbers) 41 GAL
Electrical Scope of Work Disconnects for existing electric, Temp light and power for construction, Wire 33 2x4, Wire 2 2x2, Wire 1 strip fixture in bathroom, Wire for 2 exhaust fans, Wire for 1 hot water heater, Wire for 2 lighting circuits, 2 Exits lights, 3 Emergency lights, 2 Remote heads for front and rear door emergency lights
Electrical Troffers & Materials Procure 35x New LED Troffers, all related electrical supplies + Temp Lighting & Materials 44 EA
Electrical Type A LED troffers F&I new LED troffers 35 EA
Electrical Switching 3 Single pole switches
1 Three-way system
4 EA
Electrical Switching / wiring / power 17x Duplex outlets tamper resistant, 3x GFI outlets, 2 120-volt, 20-amp Separate circuits to support the above, Electrical Underwriters Cert Fee included 24 EA
Plumbing Two ADA restroom plumbing Rough + finish plumbing for 2 toilets and 2 lavs (Owner to Pay Engineering/ professional fees for T.O.B.) 2 EA
Plumbing ADA Drinking fountain Provide drinking fountain plumbing where shown. Mount Fountain as per plans. 1 EA
Plumbing Water heater 20gal To replace existing unit near bathrooms with standard 20gal 1 LS

 

Quote

This is not a binding bid.  This is an approximation without a site visit or plans or commitment.  For a real estimate please contact us directly.  This is missing many things and generally the rate minus professional oversight, planning, permitting and due diligence.

Description Trade Scope Measure Unit  Total Price
Demolition General demo throughout, All VCT tile, ALL interior partitions, all drop ceiling and grid. Remove all existing interior NON-Load Bearing partitions (~90LF), Existing wood stud walls (CMU wall and demising ~280LF), all wall paneling, bathroom core walls, existing ACT ceiling tile/grid, Lighting and existing checkerboard/VCT floor finish throughout. (Owner will provide testing and report) 5,300 SF  $ 24,843.75
Ceilings New 2x4 ACT Panels + Grid (Materials) Procure 2x4 ACT (Rockfon Artic 601 square edge) ceiling system with 9/16" Standard white grid, hanger wire, wall angle, 2x4 ACT panels. Hung on Wire (Black Iron Excluded). 5,800 SF  $ 15,950.00
Ceilings New 2x4 ACT Panels + Grid (Labor) Furnish/install new 2x4 ACT ceiling system with 9/16" grid. NO insulation above drop ceiling. Plenum space utilities and HVAC repairs by others NOT part of this quote. Blackiron, Sprinkler and mechanical work NOT part of this quote unless specified in bid 5,300 SF  $ 36,437.50
Flooring Glue-down LVT materials Procure Owner-selected glue-down LVT (5$ per SF allowance) 5300 SF  $ 26,500.00
Flooring Glue-down LVT install labor Install glue-down LVT & cove base 5300 SF  $ 29,812.50
Carpentry Doors / frames / hardware New restroom/core doors, frames, hardware, signage where shown, Solid Core Wood Veneer, Metal Buck, Schlage Locks, as per owner supplied plan 3 EA  $   8,625.00
Carpentry Blocking / accessories backing Blocking / Mounting for grab bars, mirrors, accessories, toilet, sink 2 EA  $   3,000.00
Carpentry / Framing Restroom/core framing (up to 12ft AFF) Frame new restroom/Utility partitions and affected wall/door openings, above grid, as per plan. 3-5/8", 20 ga. metal studs at 16" O.C., 5/8" gypsum board both sides, water-resistant gypsum board on wet sides where indicated, sound attenuation batts where indicated, extending to 6" above finished ceiling. Non-Fire rated partitions. 44 LF  $   3,575.00
Carpentry / Framing Exterior and Demising wall framing (up to 12ft AFF) Frame all exterior cmu walls, demising wall, rear wall, front wall with 3-5/8", 20 ga. metal studs at 16" O.C., extending to 6" above finished ceiling. NON-Fire rated NON insulated. 357 LF  $ 20,081.25
Carpentry / Drywall Drywall Materials (up to 12ft AFF) Procure commercial 5/8" sheetrock and related materials at restroom/core and all interior walls, up to 12ft AFF. 122 SH  $   5,032.50
Carpentry / Drywall Drywall Labor (up to 12ft AFF) Hang/finish/Paint Level III, commercial 5/8" sheetrock at restroom/core and wall repairs as required. Includes Paint as per plan. Extends 12ft AFF. Fire rating and certifications NOT included (provided by owner) 122 SH  $ 28,975.00
Carpentry / Drywall/Paint Paint (Benjamin Moore Materials) Procure Paint for walls. Premium Paint Benjamin Moore "BEN" Pale Oak OC-20 eggshell or selected color. (Paint Labor to be Priced inside drywall numbers) 41 GAL  $   3,280.00
Electrical Scope of Work Disconnects for existing electric, Temp light and power for construction, Wire 33 2x4, Wire 2 2x2, Wire 1 strip fixture in bathroom, Wire for 2 exhaust fans, Wire for 1 hot water heater, Wire for 2 lighting circuits, 2 Exits lights, 3 Emergency lights, 2 Remote heads for front and rear door emergency lights
Electrical Troffers & Materials Procure 35x New LED Troffers, all related electrical supplies + Temp Lighting & Materials 44 EA  $   6,160.00
Electrical Type A LED troffers F&I new LED troffers 35 EA  $   7,437.50
Electrical Switching 3 Single pole switches, 1 Three-way system 4 EA  $   1,875.00
Electrical Switching / wiring / power 17x Duplex outlets tamper resistant, 3x GFI outlets, 2 120-volt, 20-amp Separate circuits to support the above, Electrical Underwriters Cert Fee included 24 EA  $   6,750.00
Plumbing Two ADA restroom plumbing Rough + finish plumbing for 2 toilets and 2 lavs (Owner to Pay Engineering/ professional fees for T.O.B.) 2 EA  $ 16,250.00
Plumbing ADA Drinking fountain Provide drinking fountain plumbing where shown. Mount Fountain as per plans. 1 EA  $   2,500.00
Plumbing Water heater 20gal To replace existing unit near bathrooms with standard 20gal 1 LS  $   3,500.00