Bathroom Remodel in Suffolk county
BuildingLI.com@buildingli
Quote from BuildingLI.com on 05/03/2026,This bathroom gut job took about 140 hours and about 8k in labor costs plus 4k in materials. Subway tile and natural slate floor. Total time to complete was 9 days.
Day1: Demo
Day2:Roughing, plumbing, elec.
Day3: sheathing, framing
Day4: Tile
Day5: Tile
Day6: Tile
Day7: Tile
Day8: Fixtures, trim, grout
Day9: Paint, cleanup![]()
![]()
This bathroom gut job took about 140 hours and about 8k in labor costs plus 4k in materials. Subway tile and natural slate floor. Total time to complete was 9 days.
Day1: Demo
Day2:Roughing, plumbing, elec.
Day3: sheathing, framing
Day4: Tile
Day5: Tile
Day6: Tile
Day7: Tile
Day8: Fixtures, trim, grout
Day9: Paint, cleanup
Day1: Demo
Day2:Roughing, plumbing, elec.
Day3: sheathing, framing
Day4: Tile
Day5: Tile
Day6: Tile
Day7: Tile
Day8: Fixtures, trim, grout
Day9: Paint, cleanup

BuildingLI.com
BLI Facilities - Long Island