Estimating and Planning a Bathroom Remodel on Long Island
Quote from BuildingLI.com on 10/02/2025,
- Simple 3 piece Tiled Bathroom Estimating 101:
Total 92 Hours
-Day1 (8 hours)
Provide proposal, sign contract, take deposit. Obtain finish schedule and Order materials.
-Day2 (16 hours)
Staging, Protection, Demolition, Disconnection, Cleanup
-Day3 (16 hours)
Rough Plumbing, Framing, Electrical, Water Protection, Sheathing, Patching, Carpentry, Fan and Duct
-Day4 (16 hours)
Tub, Shower or combo install, floor tile, wall tile, medicine cabinet, plumbing connections, vanity, toilet, paint
-Day5 (16 hours)
Finish work, paint, Doors and Door Hardware, Tile and Grout finish, cleanup.
*Sub Contract Plumber and Elecrical 8+4= (12 hours)
*Project Management (8 hours)
- Simple 3 piece Tiled Bathroom Estimating 101:
Total 92 Hours
-Day1 (8 hours)
Provide proposal, sign contract, take deposit. Obtain finish schedule and Order materials.
-Day2 (16 hours)
Staging, Protection, Demolition, Disconnection, Cleanup
-Day3 (16 hours)
Rough Plumbing, Framing, Electrical, Water Protection, Sheathing, Patching, Carpentry, Fan and Duct
-Day4 (16 hours)
Tub, Shower or combo install, floor tile, wall tile, medicine cabinet, plumbing connections, vanity, toilet, paint
-Day5 (16 hours)
Finish work, paint, Doors and Door Hardware, Tile and Grout finish, cleanup.
*Sub Contract Plumber and Elecrical 8+4= (12 hours)
*Project Management (8 hours)